DOVER LEISURE CENTRE PROJECT ADVISORY GROUP meeting on Thursday 8 December 2016 at 3.00 pm at Fort Whitfield!
A decision is therefore required as to
whether to:
1.
Proceed as planned
Base Scheme
No additional cost
2.
Future proof
the ability to add the
spa at a later date
Base Scheme + Spa Future Proof
Additional £288,000 excluding VAT
3.
Proceed with the Spa
as part of the
current project
Base Scheme + Spa
Additional £2,394,000 excluding VAT
4.
Proceed as planned, but increase
services capacity
Base Scheme + increased services
capacity
Additional £39,000, excluding VAT
N.B. Initial estimates suggest that the inclusion of the spa could extend the programme by AT LEAST 3 MONTHS
.
Info here:-
http://moderngov.dover.gov.uk/documents/b7960/Supplementary%20Papers%20-%20Notes%20and%20Spa%20Report%2008th-Dec-2016%2015.00%20Dover%20Leisure%20Centre%20Advisory%20Grou.pdf?T=9