DWDR progress as at 8/9th October
New Marina Pier. Can you spot the single piece of handrail that has been put in place?
The Wellington Navigation Channel & Lock
.... now has an altered temporary pedestrian walkway across the Cut
New Marina Control Building
Marina pontoon piling continues.....
The area between the Sea Sports Centre and the new Pier and Lock Cut is being developed with sets of concrete steps
This is the breakwater at the end of the Marina Curve. Not sure if the taller piling is intended to be supports for a pontoon berth but they are similar to the piling (with white caps) further down the curve that will eventually hold a floating pontoon for DHB work vessels.