    a20 road works started on the 15/5/17,brief below sets out the planed works.


    area 4 asc/cf/cc dated 17/5/17.

    we are installing new elactronic signs to allow the speed limit to varybetween the national speed limit and 40 mph when freight is being managed on the a20.
    we will be undertaking these works in 2 phases with preliminary work starting on Monday the 15th of may.

    phase 1construction and installation of the new signs stating on monday 15/5/17 and expected to last 6 weeks.

    phase 2.commissioing of the new signs starting on Monday 26 of june expected to last 4 weeks.

    we will be working 24/7 to complete the work as quickly as possible with up to 10 teams out at any one time.

    lane 1 will be closed on the London bound carriageway 24/7 for the duration of the work
    both carriageways will be closed overnight between 8pm and 6 am on some nights during the work
    all laybys at this location will be closed.